“Sorry state of affairs” as Vale Council faces up to cost of incinerator case - has it burned a lot of money?

Local News by Ted Peskett - Local Democracy Reporter 14th Jan 2024  
The incinerator
The incinerator

Vale of Glamorgan Council could stand to loose a huge chunk of money over a planning row after its enforcement notice on a Barry incinerator plant failed.

Planning and Environment Decisions Wales (PEDW) quashed the council's enforcement notice which it served against Barry Biomass UK No.2 Ltd's biomass burning plant on Woodham Road in 2021 after a number of discrepancies were found with the approved plans for the site.

Barry Biomass UK, managed by Aviva Investors, appealed the council's decision to PEDW, claiming that the notice served on it was inaccurate and disproportionate.

Another separate application by the company for costs to be paid by Vale of Glamorgan Council has now been approved by PEDW.

A decision letter published by the planning body is highly critical of the council, stating that proper investigation of the planning breach was lacking and that this failure was "compounded by repeated refusal to accept that the [enforcement notice] was defective".

PEDW's letter goes on the say that the council's "failure to correctly identify the breach of planning control" caused Barry Biomass UK to "incur unnecessary or wasted expense in pursuing the appeal".

There is no specified amount of money in the decision letter, but it states that Barry Biomass UK is now invited to submit to the council details of costs to reach an agreement over the amount.

A Vale of Glamorgan Council spokesperson said: "The Council is aware of strong local feeling regarding the Barry Biomass plant and is disappointed by PEDW's decision in respect of the Enforcement Notice served against it.

"It is now for PEDW to submit a breakdown of costs incurred in defence of the previous notice.

"Though PEDW's decision cannot be appealed, this decision will not stop the Council taking further enforcement action against the plant, should the need arise.

"Such circumstances include the plant becoming operational without planning permission or in the event that the current planning applications, due to be considered by committee, are refused."

The Docks Incinerator Action Group (DIAG) called the situation a "sorry state of affairs" and said they are not surprised by the inspector's decision.

The group maintains its stance that the incinerator must have an environmental impact assessment (EIA), adding: "We agree with the Inspector that the behaviour of the officers is unreasonable but, as always, the only people who pay the penalty are the local residents.

"We deserve better. Councillors should stop supporting the indefensible. We need a proper review of the behaviour at the Vale."

The alleged discrepancies with the original planning application, approved in 2015, included the layout and elevation of the development; additional structures, plant and equipment; and an extension of the site to the north.

Vale of Glamorgan Council said it had little choice but to serve the enforcement notice when it did as it wanted to ensure that the developers were not able to gain consent by default, which could have rendered conditions applied to the original application null and void.

New evidence brought before PEDW by Barry Biomass UK showed that there was a need to alter the notice to accurately reflect the reported planning breaches which took place.

PEDW invited the council to consider how the alleged breach could be corrected and following a Vale of Glamorgan Council planning committee meeting on April 27, 2023 committee members agreed to put forward an amendment to the enforcement notice for PEDW's consideration.

On July 17, the planning inspectorate sent a letter to the council stating that reporting on both the original notice and the suggested corrections would introduce significant additional uncertainty and complexity to the inquiry.

It added that there was a significant risk of extending the number of inquiry sitting days and the likelihood of requiring a significant period of adjournment.

A number of planning applications submitted by Barry Biomas UK to regulate the biomass burning plant will be considered by Vale of Glamorgan Council's planning committee.

However, a date has not yet been set for when these applications will be determined.

     

CHECK OUT OUR Jobs Section HERE!
barry vacancies updated hourly!
Click here to see more: barry jobs

Share:


30% OFF

Apple AirPods 2nd Gen with Lightning Charging Case and 1m Cable
Hear the difference-wireless freedom is music to your ears! Apple Earbuds 2nd Gen - Charging Case and 1m Cable
£199.95 £139.3

51% OFF

8-Seater Modern Rattan Garden Dining Set with Fire Pit Table – Weather-Resistant PE Wicker
Light up your patio and your parties with the perfect social set! 9-Seater L-Shaped Patio Set with Fire Pit from J30 Discount Furniture
£1400 £686

34% OFF

 Save  up to  63%  222 Bought PRICE DROP! Wingline Divan Bed & Mattress - 8 Colours - 2 or 4 Drawers Option View variant  Save  up to  34%  66 Bought Falcon Velvet Scatterback Sofa Range – Armchair, 2-Seater, 3-Seater & 3+2 Set | Plush Velvet Sofas for Modern Living Rooms View Selling fast! gemini_outpaint_variant_43944525  Save  69%  313 Bought PRICE DROP! Luxury Rio Divan Bed: Premium Memory Sprung Foam Mattress & Optional Storage Drawers - 6 Sizes & 10 Colours View Selling fast! variant  Save  75%  5404 Bought Crushed Velvet Divan Bed & Memory Sprung Mattress - 7 Colour Options View Selling fast! variant  Save  68%  549 Bought PRICE DROP! Plush Velvet Pure Wingback Upholstered Bed with Memory Foam Sprung Mattress View DMD Collective 20-Bar Espresso Coffee Machine with Digital Display and Milk Frother
Pull an espresso and a smile-it's café quality right at home! 20-Bar Espresso Coffee Maker with Frother
£89.99 £58.74

Sign-up for our FREE newsletter...

We want to provide barry with more and more clickbait-free news.